Switch to mobile site
Loading

Central Heating

Exam revision materials for Plumbing Level 2&3 and ACS Gas Safety test

Create an Article

Maintenance

Commissioning

Click to show/hide index

Maintenance

Commissioning

Heating system water analysis

Servicing

Controls

Circulating Pump

Heating System Controls

Minimum Requirements

Room Thermostats

Regulations

Regulations

Heat Emitters

Heat Loss Calculation

Radiator Sizing

Types

Pipework

Fully Pumped Hot Water and Central Heating

Gravity Hot Water and Pumped Central Heating

Gravity System

Open-vented System

Pipework Sizing

Pipework Systems

Sealed Systems

System Layout

Underfloor Heating

Boilers

Boiler Sizing

Flue Types

Gas Boilers

Heat Pumps

Oil Fired Boilers

SEDBUK Rating

Solid Fuel Boilers

Water Treatment

  1. Visual Inspection
  2. Fill the system
  3. Pressure test the pipework to be concealed
    • at 1.5 times the working pressure
    • or 3 bar whichever is greater
    • for 1 hour
  4. Replace the Pump with a piece of pipe
  5. Fill up the system, check for leaks and drain it down
  6. Fill the system with a Flushing Agent (cleaner) and heat
    • The hot flush is recommended for 2 hours for the cleaning operation (flux residues)
  7. Re-fill the system applying Corrosion Inhibitor
    • Inhibitor must not be added to the primary circuit of single feed indirect cylinder
  1. Check that flow pipe runs at 80°C and the return at 70°C
  2. Check for correct combustion with Gas Flue Analyser
  3. Fill out the Benchmark logbook
    • Gas Safe Registered (former CORGI) ID card serial number should be always included
  4. Instruct the customer how to use the controls
  5. Leave all relevant literature with the customer